Latest Traffic Update For Manatee and Sarasota Counties – Sarasota Manatee MPO

 

 

MANATEE COUNTY

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, and SR 70. Crews are also working on the retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect single lane closures on I-75 during nighttime/overnight hours from 7 p.m. to 7 a.m. and double lane closures from 8 p.m. to 6 a.m. through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

US 301 at Erie Road/Old Tampa Highway: Construction project: Crews are making improvements to the intersection. Motorists should expect daytime and nighttime lane closures on westbound US 301 from 12 p.m. to 5:30 a.m., and eastbound on US 301 from 7 p.m. to 2 p.m. while crews are working. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

US 301 at 121st Avenue: Maintenance permit project: Crews are constructing a driveway and right turn lane. The outside westbound lane will be closed from 9 a.m. to 4 p.m. daily beginning Monday, July 20 through Friday, September 4. Use caution and expect possible delays.

US 19 from US 41 to Terra Ceia Road: Construction project: Crews are resurfacing the roadway, improving drainage and constructing sidewalk. Expect daytime single lane closures between 9 a.m. and 4 p.m. and nighttime/overnight lane closures between 7 p.m. and 6 a.m. throughout construction. AJAX Paving Industries of Florida is the contractor. Expected completion is early 2021.

SR 684/Cortez Road from 123rd Street W to 119th Street W and from 123rd Street W to 86th Street W: Construction project: Crews are realigning the intersection of SR 684/Cortez Road and 119th Street W, resurfacing the roadway, improving drainage, constructing sidewalk and installing new highway lighting. Expect nighttime/overnight lane closures from 10 p.m. to 6 a.m. on SR 684/Cortez Road and on 119th Street W (both north and southside). Daytime lane closures from east of 119th Street W to 86th Street W within the four-lane section of SR 684/Cortez Road are expected from 8 a.m. to 4 p.m. over the next few weeks. AJAX Paving Industries of Florida, LLC is the contractor. Expected completion is late fall 2020.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. Traffic has been shifted to the southside of SR 64 with one 10 foot lane in each direction. The speed limit on State Road 64 has been reduced to 25 mph within the construction zone. A new traffic pattern is expected to be implemented on Wednesday, July 22. This new traffic pattern will shift traffic into the roundabout configuration.  Motorists should use caution and pay close attention to the change in traffic patterns. IBT Construction is the contractor. Expected completion is summer 2020.

SR 64 eastbound at 11th Street W: Construction project: Crews are resurfacing the roadway, constructing sidewalk, improving lighting and signalization, and installing new signing and pavement markings. Expect nighttime/overnight single lane closures on westbound SR 64 from 7:30 p.m. to 6 a.m. while crews are working. Expect single lane closures on eastbound SR 64 from 9 a.m. to 4 p.m. and from 7 p.m. to 6 a.m. while crews are working. American Lighting and Signalization, LLC is the contractor. Expected completion is summer 2020.

 

SARASOTA COUNTY

I-75 at SR 681, SR 758/Bee Ridge Road, and SR 780/Fruitville Road: Maintenance project: Crews are installing new components on the high mast light poles. This week, crews will be preparing the site for the upgrades and start pole replacement.  The contractor is Ajax Paving Industries of Florida, LLC. Expected completion is late July 2020; weather permitting.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Daytime lane closures are expected throughout the project limits.
  • Curb installation in the median area and 14th Street and 10th Street roundabouts is expected throughout the week. Work is scheduled during the daytime. Please be cautious of construction vehicles, concrete trucks, pickup trucks and crews working close to travel lanes and entering and leaving the travel lanes.
  • Truck aprons are scheduled to be installed at 10th Street and 14th Street roundabouts over the next 2 weeks. Work is scheduled during the daytime. Traffic going through the roundabouts will be impacted, with some of the movements being restricted.
  • Irrigation pipe installation in the median is expected to continue throughout the week.
  • Soil installation is expected in the medians. Expect dump trucks unloading material in the median.
  • Drainage pipe installation is expected to continue on 10th Street between US 41 and Cocoanut Avenue. Expect noise from construction equipment and trucks entering and leaving the travel lanes. Impacts to The Jefferson Center driveway are expected during the installation. Ingress and egress to the parking area will be coordinated with the building management.
  • Asphalt paving will occur throughout the week along median areas and 13th Street. Work is scheduled during the daytime. Please be cautious of construction vehicles, asphalt trucks and crews going in and out of the medians. Lane closures will be present during this work.
  • Traffic signals on US 41 at 10th Street and 14th St have been removed, and motorists shall follow roundabout signage and driving conditions.
  • Sidewalk on the west side and east side of US 41 between 10th Street and 14th Street are open for public access. Pedestrians are advised to use the designated sidewalks and crosswalks. Intermittent sidewalk closures are expected as crews work in the areas.
  • Installation of conduit, poles, signalization cabinets and streetlighting throughout the project corridor. Be cautious of equipment, bucket trucks and crews working next to the roadway.
  • No left turns permitted within the project limits, except at the boat ramp, which has an exclusive left turn lane for north bound traffic.
  • Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.
  • Motorists are urged to use caution and watch for trucks and other construction equipment within the work zone.
  • Expect noise from excavators, vibration from rollers, back up alarms, trucks, and construction vehicles throughout the project corridor.
  • Work is expected during daytime hours, but some activities will require weekend and nighttime work.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a six-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is fall 2020. The contractor is IBT Construction LLC.

US 41 (Venice Bypass) from Center Road to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb and sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. The contractor is Bergeron Land Development, Inc. Expected completion is spring 2021.

  • Beginning as early as end of July, crews will shift traffic from the existing southbound lanes of US 41 from Center Road to Gulf Coast Boulevard to the west onto the newly paved roadway.
  • Crews may shift all pedestrian traffic to the newly constructed sidewalk on the west side of the roadway as early as Monday, July 19.
  • Please use caution when traveling through the project corridor as the median has narrowed.
  • Motorists should expect temporary northbound and southbound lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 a.m. to 11 p.m. Sunday, July 19, to Saturday, July 25, to perform drainage pipe installation.
  • Crews are working within business driveways and in the right-of-way along the southbound lanes of US 41. Please watch for crews, use caution and follow flagger directions when turning into businesses and shopping plazas.

US 41 from First Street to Boulevard of the Arts, and on Fruitville Road from US 41 to Cocoanut Avenue: Construction project: Crews are constructing a roundabout at US 41 and Fruitville Road, a 12-foot multi-use trail on the west side of US 41 and a variable-width sidewalk on the east side of US 41; replacing existing underground drainage and utility structures, and installing new LED streetlights and landscaping. Other improvements include raised pedestrian refuge islands and a HAWK pedestrian signalization system. Use caution and watch for changes in the traffic pattern. Wright Construction, Inc. is the contractor. Expected completion is fall 2020.

  • Beginning Sunday, July 19, through Saturday, July 24, expect possible intermittent daytime and nighttime lane closures on US 41 between First Street and Boulevard of the Arts for roadway work.
  • Beginning in early August, crews will establish a new traffic pattern that will shift northbound US 41 traffic from the existing travel lanes on the west side of the roadway to newly paved travel lanes on the east side of US 41. Southbound US 41 traffic will remain in its current configuration. To prepare for this new traffic pattern, crews may temporarily close the eastbound lane of Fruitville Road beginning as early as the week of Monday, July 27. This closure will remain in effect until the new traffic pattern is established.
  • The travel lanes on US 41 from Boulevard of the Arts to First Street have been shifted to the west side of the roadway onto a new diversion road. Two lanes of traffic have been maintained in each direction during daytime operations. Due to this traffic shift, the following maintenance of traffic is in effect:
    • Westbound Fruitville Road is closed to all traffic from Cocoanut Avenue to US 41 (in effect through summer 2020). Motorists desiring to reach US 41 from westbound Fruitville Road will need to turn right onto Lemon Avenue, follow Lemon Avenue to 10th Street, then follow 10th Street to reach US 41. Detour signage is in place.
    • No left turns are allowed from southbound US 41 to eastbound Fruitville Road (in effect through fall 2020).
    • Southbound motorists, if desiring to go east from US 41, will need to turn left at 10th Street, follow 10th Street to Lemon Avenue, turn right at Lemon Avenue and then follow Lemon Avenue to Fruitville Road. Detour signage is in place.
    • There is no access from US 41 to Fourth Street or the alleys located between First Street to Fifth Street.

US 41 from River Road to Woodmere Park Boulevard: Construction project: Crews are constructing sidewalk and bus shelter pads; installing guardrail and lighting and improving drainage. Motorists should expect daytime lane closures from 9 a.m. to 4 p.m. and nighttime lane closures from 7 p.m. to 6 a.m. while crews are working. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2020.

US 41 from Blackburn Point Road to Preymore Street: Construction project: Crews are resurfacing the roadway, replacing the US 41 northbound bridge over North Creek, improving drainage, constructing sidewalk and installing new highway lighting. Expect nighttime/overnight northbound lane closures from 6 p.m. to 6 a.m. and nighttime/overnight southbound lane closures from 6:30 p.m. to 9:30 a.m. Northbound traffic will shift to one of the southbound lanes, reducing traffic to one lane each direction. The traffic shift is expected to be in place for approximately eight months while crews reconstruct the northbound bridge over North Creek. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.